View full announcement with attachments

31 March 2022
This Amendment extends the due date for the the COBRa RFPP to 19 April 2022. Additionally, there are also changes to to sections 1.3, 1.4, 2.4, and 4.6. Also there are additional Government responses to member questions. Please refer to the documents section of this opportunity for all updated information.   

25 March 2022 Amendment 03
This Amendment is to provide Government responses to member questions only. There are no other changes to the Project Announcement. For any questions about this amendment, please contact Bill Wilson, SCEC Program Manager, at bwilson@sossecinc.com.

8 March 2022 Amendment 02
This Amendment extends the due date on questions related to the Project Proposal. The new due date is 17 March 2022. It also extends the submission deadline to 4 April 2022 at 3 PM ET.
Additionally, Section 7.2 of the Request for Project Proposal document has been updated. For any questions about this amendment, please contact Bill Wilson, SCEC Program Manager, at bwilson@sossecinc.com.

7 March 2022 Amendment 01
This Amendment extends the due date on questions related to the Project Proposal. The new due date is 15 March 2022. Additionally, two CUI documents have been added to the documents section (Attachments 15 and 16). Please reach out to Bill Wilson, SCEC Project Manager, at bwilson@sossecinc.com if you have any additional questions.

Project Title Combat Operations Battlefield Radar (COBRa) Prototype
Announcement Number SCEC-22-0001
Announcement Type Request for Project Proposal (RFPP) – Amendment 04
Federal Agency Name ACC-APG Belvoir
Entity Name SOSSEC, Inc. and the Sensors, Communications and Electronics (SCEC) Consortium
Release Date 24 February 2022
Closing Date/Time 19 April 2022 @ 3 PM ET   04 April 2022 @ 3 PM ET 
Page Count Volume 1 of the proposal submitted in response to this RFPP should be no more than 25 pages in length.
Individual Awards A single award is anticipated under this announcement. The Government reserves the right to select all, part, or none of the proposals received, subject to the availability of funds. All potential Offerors should be aware that due to unanticipated budget fluctuations, funding in any or all areas may change with little or no notice
Instrument Type Expenditure-based Project Level Agreement. An expenditure-based instrument will contain a payable milestone delivery/payment schedule with amounts to be adjusted based on generated information from financial or cost records. Funding arrangements are at the discretion of the Government.
Anticipated Value

(These dollar figures include the SOSSEC OT-Lead Fee of 3.25% applied to Price)

Total Funding for this Project Announcement is $35,000,000. Funding breakdown is provided in paragraph 3.1 of Attachment No 1. The Government reserves the right to make awards up to any dollar value.
Period of Performance The period of performance is estimated to be seventy-two (72) months from project award date, commencing approximately May 2022 and concluding on/around May 2028.
Questions and Submissions All Questions and Project Proposals submissions must be submitted in accordance with instructions in Section 1.0 Special Notices below NLT 17 March 2022
Attachments ·          Amendment 04 – Attachment-8-SCEC-Q-A-Version-1.0 – ANSWERS CP v1 03-31-2022

·         Amendment 04 – SCEC-22-0001 COBRa RFPP FINAL 03-07-2022 (AMD 03)v2

·         Amendment 03 – Attachment-8-SCEC-Q-A-Version-1.0 – ANSWERS CP v1 03-23-2022

·        Attachment No. 1 CUI for RFPP SCEC-22-0001

·        Attachment No 2. Classified Performance Characteristics Documents (PCD) of COBRa

·        Attachment No. 3 DRAFT DD254 for COBRa (with SCGs attached)

·        Attachment No. 4 Statement of Objectives (SOO) of COBRa

·        Attachment No. 5 Classified Annex A to the SCG for Fires Radar and Technology Efforts

·        Attachment No. 6 Deliverables

·        Attachment No. 7 SCEC OTA Flow-Down Articles

·        Attachment No. 8 Q & A Template

·        Attachment No.  9 SCEC Cost Proposal Template

·        Attachment No.  10 SCEC Milestone Delivery Schedule Template

·        Attachment No. 11 Non-Traditional or Traditional Warranties and Representations

·        Attachment No. 12 Standard Form 298, upon project completion

·        Attachment No. 13 SCEC Cost Proposal Instructions

·        Attachment No. 14 SCEC Proposal Cover Sheet

·        Attachment No 15 CUI TARDEC Active Protection Technology SCG 10JUL2017

·        Attachment No 16 CERDEC Fires Radar S&T SCG 19JUN2018

It is the responsibility of the submitting party to confirm receipt of submissions by SOSSEC Inc., Please send a transmittal via email to SOSSEC Inc after submitting all CUI/Classified proposals and Questions.  Emails must reference the Project Announcement Number and Project Title of the OTA Project. CUI Attachments are highlighted in Yellow; Secret Documents are in Red